FGT Critical Notice

Notice ID: 54207
Notice Type: Maintenance
Critical: Y
Notice Status Description: Initiate
Reqrd Rsp Desc: No Response Required
Posting Date/Time: Jun 19 2025 12:15PM
Subject: UNPLANNED PIPELINE MAINTENANCE IN ZONE 1 – FIRST UPDATE
Notice Effective Date/Time: Jun 19 2025 12:15PM
Notice End Date/Time: Jun 20 2025 9:00AM
Notice Text:

FGT’S unplanned pipeline maintenance in the pipe segment just east of FGT Station 6 has been completed and is back in normal operation. During normal operations FGT schedules up to 300,000 MMBtu/day through Station 6. Normal volumes through Station 6 can now be scheduled for the gas day of June 19, 2025. The following points are now available:

Golden Triangle Storage Receipt (POI 78523), Normal Capacity: 250,000 MMBtu/day

Golden Triangle Storage Delivery (POI 78524), Normal Capacity: 200,000 MMBtu/day

Golden Pass Receipt (POI 78503), Normal Capacity: 250,000 MMBtu/day

Enbridge Orange (POI 78499), Normal Capacity: 200,000 MMBtu/day